The fertilizer project has had a few setbacks due to the weather but is still on track to be operational in the spring of 2026. 

Here are a few updates completed recently!

1. Electrical lines and transformers are in place to provide temporary power and eventually permanent power to the plant.

2. The soil correction has been completed by digging down 11’ to replace the native soil with a more stable clay/dirt mix.

3. The process of forming the footings is being completed now for a cement pour in the coming days.

4. The footings will be completed at the same time the foundation for the tower is completed.

We are excited to share more updates moving forward as this project continues to progress!

Our mission is to be our customers first choice for industry-leading resources and knowledge.









 

Read More News

Aug 04, 2025

We’re excited to share that we’ll be launching a new digital portal designed to make it easier for you to access account information, make payments, and stay connected with us.

Jul 28, 2025

Lock in low rates now and stay ahead of winter demand.

Jun 27, 2025

It’s been a busy week in Hecla, and we’re excited to share some major progress!

Related Topics