Hecla Fertilizer Plant Update

Aug 14, 2025


The fertilizer project has had a few setbacks due to the weather but is still on track to be operational in the spring of 2026. 

Here are a few updates completed recently:

1. Electrical lines and transformers are in place to provide temporary power and eventually permanent power to the plant.

2. The soil correction has been completed by digging down 11’ to replace the native soil with a more stable clay/dirt mix.

3. The process of forming the footings is being completed now for a cement pour in the coming days.

4. The footings will be completed at the same time the foundation for the tower is completed.

We are excited to share more updates moving forward as this project continues to progress!

Our mission is to be our customers first choice for industry-leading resources and knowledge.









 

Read More News

Jun 25, 2026

We’re excited to help you get ahead of the heating season with our Summer Fill propane program: The best opportunity of the year to lock in the lowest price of the season and plan with confidence.

Jun 25, 2026

Managing your account has never been easier. With autopay and digital statements, you can save time, stay organized, and eliminate the hassle of paper and manual payments.

Jun 10, 2026

As a member-owned cooperative, Full Circle Ag is committed to making decisions that strengthen our organization and create long-term value for the member-owners and communities we serve. After careful evaluation, we have made the decision to...

Related Topics